thumbnail_IMG-4901

Farallon Island Roof Replacement

Location: Farallon Island, CA
Completion Date: 10/10/2024
Customer: US Fish and Wildlife Service
Contract Amount: $651,129

Description of work: Reroof two houses located 30 miles offshore from the mainland. We removed two layers of shingles, new plywood decking, installed roof ventilation, removed and replaced gutters, removed old attic insulation and replaced it wil blow-in cellulose.

All materials to and from the island were moved by helicopter. We moved approximately 50,000 pounds to the island and brought back 35,000 pounds. All project personnell were transported via helicopter. Moving freight to and from the island required coordination of 11 people on shore for traffic control and public safety.

 

Let's Connect